User Tools

Site Tools


schedule

This is an old revision of the document!


AGL Schedule and Milestones

Release Schedule Overview

AGL follows a twice per year release cadence. This is split in 3-4 month of feature development plus a freezing process in stages.

New Feature Development

Once a new release is started the initial work will be to update meta-agl master to the planned Yocto branch for the release. Once this is complete for then new feature branches will be accepted on master. Each of these subphases will be announced on the automotive-discussions.

Release Candidates

The first stage is the core feature freeze, followed by RC1. Next is then the 2nd stage which is the platform freeze which feeds into RC2. Finally there is a apps/docs/tests freeze right before RC3. After final stabilization, the release will be cut.

Example release schedule

The next pictures explain the workflow in detail:


Latest Schedule


Happy Halibut


Itchy Icefish

Jumping Jellyfish

Kooky Koi

Archive

2019 Schedule

2018 Schedule

2017 Schedule

schedule.1593207268.txt.gz · Last modified: 2020/06/26 21:34 by wminer